Change Control Process

While requirements are well defined as coding starts, any project involving software is by its nature elastic.  At times, changes may push the project beyond the bounds under which this proposal was accepted.  For these situations, Nihilent Sapphire Inc provides a formal Change Control Management Process.

 

Should you wish to change the specification, you will use a Change Control Note that :

Assigns a reference number to the change for tracking.
Defines the change.
Shows the time/cost effect on the project.
Documents acceptance of the change by both Sapphire and you

No change is made without Sapphire providing a written quotation for the work and the receipt of written acceptance of the quotation from you.